(21, February, 2005)
Contract of Several domestic projects Busan Line # 3, DaeJeon Line # 1, and KNR Extension project On the 6th of April, 2004, Yujin contracted key components (Brake System, Driving Gear, Coupler, Pantograph, etc) of Busan Line #3 80cars, Deajeon Line #1 84cars, and KNR 20cars with Rotem Company. * The Delivery Schedules of above three projects are as below. 1) Busan Line #3 : From 10th of July, 2004 to 10th of March, 2005. 2) Daejeon Line #1: From 10th of August, 2004 to 10th of April, 2005. 3) KNR 20cars : From 20th of June, 2004 to 20th of August, 2004. Because of above projects, Yujin strengthened its competitiveness in Domestic Rail Business. |